Update of Water Recycling Project

The water recycling workshop/laboratory has been quite a project the last tfour months.  Many events have slowed the project; in particular, the deaths of Steve Mcgraw and my Dad.  Also, the design and building permitting took longer than expected.  The excavation took longer due to the primary contractor backing-out, and hitting a big rock.  The foundation and roofing took longer due to the necessity for engineering drawings (Stiffler-Mcgraw bailed the project out).  Yet, all the concrete work is done and we are ready for the electrical.  Also, today was the first day of construction for the recycling shower prototype.  By Thanksgiving, we hope to have the electrical installed, the foundation covered for winter and the recycling shower ready for concept testing.  By the end of the year, we hope to have the laboratory ready for commercial testing, and hope to undertake a more agressive marketing of the facility.  The team continues to work hard and DEP continues to drag its feet (11/10/08).